Project

General

Profile

Actions

Bug #8658

closed

Bug #8458: Regression: Program issues faced in Program view. (Refer the comments section updated with impact issue also)

Regression : Program issues

Added by Anonymous over 6 years ago. Updated over 6 years ago.

Status:
Closed
Priority:
Medium
Assignee:
Start date:
10/29/2018
Due date:
% Done:

100%

Estimated time:
(Total: 0:00 h)
Steps To Reproduce:

1)Login as Program manager
2)Create and Observe the Program planner view

MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 4
Customer:
Issue Dependency:
Dev Commitment to Resolve in::

Description

1)Predecessor is not displayed based on the deliverable number it is displayed same for
all the projects which is imported.(Refer screenshot) - Not Fixed.
2)When the Project is imported with the template, then in the project planner it is displayed in the red color by default.
the project associated with the programs are not even started or plan not published.
3)% in the Program listing screen is differs with the task and effort based completion with more difference.


Files

Program Colour indication.png (191 KB) Program Colour indication.png Anonymous, 09/27/2018 06:18 PM
Program Predecessor.png (212 KB) Program Predecessor.png Anonymous, 09/27/2018 06:18 PM
Program _ in listing screen.png (79.7 KB) Program _ in listing screen.png Anonymous, 10/03/2018 11:41 AM

Subtasks 1 (0 open1 closed)

Bug #9573: Regression: Program - % in the Program listing screen is differs with the task and effort based completion with more difference.ClosedVaradharaj S10/29/2018

Actions
Actions #1

Updated by Anonymous over 6 years ago

  • Status changed from New to Open
Actions #2

Updated by Anonymous over 6 years ago

Actions #3

Updated by Varadharaj S over 6 years ago

  • Status changed from Open to Resolved

2. WAD

Actions #4

Updated by Anonymous over 6 years ago

  • Status changed from Resolved to Yet to Verify
Actions #5

Updated by Anonymous over 6 years ago

1)Predecessor is not displayed based on the deliverable number it is displayed same for
all the projects which is imported.(Refer screenshot) - Fixed
2)When the Project is imported with the template, then in the project planner it is displayed in the red color by default. - Need to discuss with senthil
the project associated with the programs are not even started or plan not published.
3)% in the Program listing screen is differs with the task and effort based completion with more difference -Need to discuss with senthil

Actions #6

Updated by Smitha V over 6 years ago

  • Status changed from Yet to Verify to TBD
Actions #7

Updated by Varadharaj S over 6 years ago

  • Status changed from TBD to Resolved
Actions #8

Updated by Anonymous over 6 years ago

  • Status changed from Resolved to Fixed with Hotfix

It differs by 1 % with the effort based completion.

Actions #9

Updated by Anonymous over 6 years ago

1)Predecessor is not displayed based on the deliverable number it is displayed same for
all the projects which is imported.(Refer screenshot) - Fixed
2)When the Project is imported with the template, then in the project planner it is displayed in the red color by default.
the project associated with the programs are not even started or plan not published - Fixed
3)% in the Program listing screen is differs with the task and effort based completion with more difference - Not Fixed

Actions #10

Updated by Anonymous over 6 years ago

  • Status changed from Fixed with Hotfix to Resolved
Actions #11

Updated by Anonymous over 6 years ago

  • Status changed from Resolved to Closed
Actions

Also available in: Atom PDF