Actions
Bug #4716
closedReport : (Impact) project summary report: Project actual finish date is displayed when there is a deliverable which is not started and completed.
Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
02/12/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login into EWIQMS Application
2)Select APQP Module
3)Select reports tab
4)Click on Project Summary menu
5)Provide necessary details
6)Click on View report
7)Observe the result
MODULES:
APQPPPAP MGR
Build Cycle:
Reports
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
750
Description
Report : Project summary report: Project actual start date and finish date column displayed empty.
But there is a new impact issue in the project actual finish date column.
when there is a deliverable which is not started and completed, the project actual finish date is displayed.
Project summary report filter is not working(Project not listing as per the pillar selection)
Files