Project

General

Profile

Actions

Bug #1941

closed

"Enable Task/Effort Driven" icon is enabled for task owners with Project rights

Added by Anonymous almost 8 years ago. Updated almost 8 years ago.

Status:
Closed
Priority:
Medium
Assignee:
Start date:
06/21/2017
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

Prerequisite: Grant project rights to a task owner.
1. Login to EwQIMS as a task owner.
2. Navigate to APQP module.
3. Open the project assigned to a task owner.
=> "Enable Task/Effort Driven" icon is enabled and the task owner is change it accordingly.

MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::

Description

"Enable Task/Effort Driven" icon is enabled for task owners with Project rights. The task owner should not have an access to enable task/effort driven approach for the project. Only the Project manager should be given this access.


Files

Actions

Also available in: Atom PDF