Actions
Bug #16044
closedGRR-Multi parameter- Actions->(Central - IST)--> When tries to conduct the study for multi parameter, the due date for both parameter shows wrongly. Kindly refer screenshot
Start date:
04/02/2020
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1. Login EwQIMS as MSA module administrator
2. Click on GRR menu with multi parameter
3. Conduct the study
4. Click on action menu
5. Observe the due date
MODULES:
MSAPRO
Build Cycle:
Cycle 10
Customer:
TSC & HUSCO
Issue Dependency:
SP925.3
Dev Commitment to Resolve in::
Description
GRR-Multi parameter- Actions->(Central - IST)--> When tries to conduct the study for multi parameter, the due date for both parameter shows wrongly. Kindly refer screenshot
Files