closedInprocess Inspection :If multi-operations are selected Operations and characteristics mapped in Inspection sheet is incorrect form what actually mapped in Control plan
Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
01/14/2020
Due date:
% Done:
100%
Estimated time:
Steps To Reproduce:
1.Go to IC
2.Click on Inprocess Inspection
3.Click on Operations
4.Select multiple operations in Inspection entry pop-up
5.Click on submit
6.Observe the operation and characteristics mapped to it in Inspection sheet
MODULES:
IC
Build Cycle:
Cycle 4
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
Inprocess Inspection :If multi-operations are selected Operations and characteristics mapped in Inspection sheet is incorrect form what actually mapped in Control plan