Actions
Bug #7891
closedReports→Concern data/Dumb report: Refer desc & screenshot
Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
08/25/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
refer screenshot
MODULES:
PS
Build Cycle:
Cycle 2
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
1.Concern end date is not displayed (refer screenshot)
2.Aging in days :
Observation : Aging in days is calculated including till current date
Expected : Aging in days should display number of days taken for from Concern reported date to concern closed date (total duration)
Files
Actions