Actions
Bug #6176
closedSilverlight to J-Query Conversion- When the periodic update is changed from 100 to 0, actual start date still displaying in the project planner even after refresh also.
Start date:
06/08/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Open the project
2)Modify the task progress from 100-0
3)Now click on refresh button
4)Observe the result
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
When the periodic update is changed from 100 to 0, actual start date still displaying in the project planner even after refresh also.
Files
Updated by Anonymous almost 7 years ago
Not able to verify because of periodic update issue.
Updated by Anonymous almost 7 years ago
- Status changed from Resolved to Yet to Verify
Updated by Anonymous over 6 years ago
- Status changed from Yet to Verify to Not Resolved
Updated by Anonymous over 6 years ago
- Project changed from SP810 Dev Build to SP810 - QA build
- Build Cycle changed from Cycle 3 to Cycle 1
Updated by Anonymous over 6 years ago
Not working
Refer project name : New product development
Updated by Varadharaj S over 6 years ago
- Status changed from Not Resolved to Resolved
Not Replicated
Updated by Anonymous over 6 years ago
- Subject changed from JQUERY: When the periodic update is changed from 100 to 0, actual start date still displaying in the project planner even after refresh also. to Silverlight to J-Query Conversion- When the periodic update is changed from 100 to 0, actual start date still displaying in the project planner even after refresh also.
Updated by Anonymous over 6 years ago
- Status changed from Resolved to Fixed with Hotfix
Updated by Anonymous over 6 years ago
- Status changed from Fixed with Hotfix to Resolved