Actions
Bug #6039
closedRegression - When the task progress has been started, then it should not allow to set SS and FS predecessor to that task.
Start date:
05/24/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login to EWQIMS application
2)Select APQP module
3)Open the project in mydeliverable list
4)Double click on Percentage column
5)Update the percentage
6)Now set the predecessor for that task(SS,FS)
7)Observe the result
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
When the task progress has been started, then it should not allow to set SS and FS predecessor to that task.
Files
Updated by Anonymous almost 7 years ago
- Status changed from TBD to Open
As per the discussion with sabu : If predecessor is set for the task which is already started then reduce the task progress to "Zero".
Updated by Anonymous over 6 years ago
- Project changed from SP810 Dev Build to SP810 - QA build
Updated by Anonymous over 6 years ago
- Build Cycle changed from Cycle 3 to Cycle 1
Updated by Anonymous over 6 years ago
- Subject changed from When the task progress has been started, then it should not allow to set SS and FS predecessor to that task. to Regression - When the task progress has been started, then it should not allow to set SS and FS predecessor to that task.
Actions