Actions
Bug #5002
closedInspection Entry/Receiving Inspection: Cant able to continue the Final/Receiving Inspection
Status:
Closed
Priority:
High
Assignee:
-
Start date:
03/02/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1.Goto EwQIMS
2.Login as IC Module User
3.Navigate to IC Module
4.Goto Actions Tab and Click on Inspection Entry/Receiving Inspection Menu
5.Click on the Inspection Entry
6.Fill all the required fields
7.Click on Submit Button
8.Observe the Results
MODULES:
IC
Build Cycle:
Cycle 6
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
In the Inspection Entry and Receiving Inspection Menus, by Clicking on the Submit Button after entering the Values in the Mandatory fields its not opening the Form Sheet to Inspect the Lot and the Submit Functionality is not working.
Note: Its a Showstopper Issue.