closedDVP&R - Date format is accepted as 01/01/2018. Does not accept 1/1/2018. system displays a grey colour status icon on VOC
Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
01/06/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1.Click on DVP&R
2.Enter date format as 1/1/2018 and assign Test Instance status
3.Click on VOC tab and Observe the result
MODULES:
RFD
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
DVP&R - Date format is accepted as 01/01/2018. Does not accept 1/1/2018. system displays a grey colour status icon on VOC