Actions
Bug #30384
closedFailure Analysis - After adding the failure flowdown, it is linked to the above branch, and the requirement flowdown for the other branch is only displayed after collapsing and expanding.(Refer Description)
Start date:
03/17/2025
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1. Log in to the VDA.
2. Select the Functional Analysis.
3. Select the Production Item.
4. Add two Requirements for the Function.
5. Add the same Requirement Flow down.
6. Add the Failure for one focus requirement.
7. Right-click on another flow-down branch and add the Failure.
8. Observe the Result.
MODULES:
VDA
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
ISSUE TYPE:
Description
Failure Analysis -
1. Two requirements were added for the function.
2. The same requirement flow down is added.
3. A failure was added for one focus branch, but the failure flowdown is displayed for another branch.
4. After adding the failure flowdown, it is linked to the above branch, and the requirement flowdown for the other branch is only displayed after collapsing and expanding.
Files
Updated by Gopinath Ramamoorthy about 2 months ago
- Status changed from Resolved to Not Resolved
Updated by Reng Raj about 2 months ago
- Status changed from Not Resolved to Fixed in Dev
Updated by Reng Raj about 1 month ago
- Status changed from Fixed in Dev to Resolved
Updated by Gopinath Ramamoorthy about 1 month ago
- Status changed from Resolved to Not Resolved
Updated by Gopinath Ramamoorthy 23 days ago
- Status changed from Resolved to Closed
Impact issue is there
Actions