Actions
Bug #29321
closedExport to Excel- Excel data is not showing properly if there is a number followed by the special character
Start date:
11/06/2024
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1. Login as PM
2. Enter data in plan with special character and number combination
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 0
Customer:
Issue Dependency:
11.3.0
Dev Commitment to Resolve in::
How do we missed in Testing ?:
Description
When the project contains WBS with more than 2 levels or if there is any data entered in the column project plan with special character followed by number then the excel is showing in date field(Eg: Gate Review-1)
Updated by Preethi A 5 months ago
Testcase related to this issue is
https://testlink.ewqims.net/linkto.php?tprojectPrefix=EwQIMS&item=testcase&id=EwQIMS-5858
Actions