In D1, Target Closure Date, it calculates 57 dates instead of 56 Days

Added by Rupa K 11 months ago. Updated 10 months ago.

Status:
New
Priority:
Medium
Start date:
07/25/2024
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

1. Log in as Admin
2. Go to PS
3. Open Actions
4. Click on Problem Solving phase
5. Click on D1
6. Observe the result

MODULES:
PS
Build Cycle:
Cycle 1
Customer:
Android
Issue Dependency:
Dev Commitment to Resolve in::

Description

In D1, Target Closure Date, it calculates 57 dates instead of 56 Days

Actions #1

Updated by Rupa K 10 months ago

  • Project changed from All Customer Issues to Customization