TSR-After deallocating the older ASIL from the FSR, technical functions and requirements of an allocated element with the previous ASIL still appear for the changed ASIL allocation.

Added by Vani Kunnatheri 11 months ago. Updated 8 months ago.

Status:
Closed
Priority:
Low
Assignee:
Start date:
05/29/2024
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

1.Log into FST
2.Select FSR page from the Menu
3.Add a function and Requirement against a safety goal.
4.Allocate to one element an ASIL value .
5.Go to TSR page.
6.Add two functions and Requirements against the Element.
7.Go to FSR and Deallocate the ASIL
8.Please observe the TSR
9.Re allocate other ASIL value for the same element.
10.Go to TSR and observe.

MODULES:
FST
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::

Description

After deallocating the older ASIL from the FSR, technical functions and requirements of an allocated element with the previous ASIL still appear for the changed ASIL allocation.

Tried Deallocate, then assign a new one instead of directly changing the ASIL.

Allocated ASIL D for ECU in FSR
Added two functions and Requirements in TSR page
Deallocated ASIL D from FSR , and Functions and requirements along with ASIL removed from TSR.
Allocated a non standard B for ECU , the same functions and requirements existed for ASIL D showed up.


Files

Technical functions and requirements with ASIL D.png (58.6 KB) Technical functions and requirements with ASIL D.png Vani Kunnatheri, 05/29/2024 09:19 PM
Deallocating ASIL D.png (69.1 KB) Deallocating ASIL D.png Vani Kunnatheri, 05/29/2024 09:19 PM
TSR after Deallocating.png (47.4 KB) TSR after Deallocating.png Vani Kunnatheri, 05/29/2024 09:20 PM
Allocated ASIL C.png (125 KB) Allocated ASIL C.png Vani Kunnatheri, 05/29/2024 09:20 PM
same functions and requirements showing up.png (57.9 KB) same functions and requirements showing up.png Vani Kunnatheri, 05/29/2024 09:20 PM
Actions #2

Updated by User Admin 11 months ago

  • Status changed from New to Open
Actions #3

Updated by Reng Raj 11 months ago

  • Assignee changed from chitra Kalangiam to Manivannan Uppiliappan
Actions #4

Updated by Manivannan Uppiliappan 11 months ago

  • Assignee changed from Manivannan Uppiliappan to Manoj Kumar
Actions #5

Updated by Shankar Narayanan 10 months ago

  • Project changed from SP 11.2.0.15 Patches to SP 11.2.0.16 Patches
Actions #6

Updated by chitra Kalangiam 10 months ago

  • Status changed from Open to Resolved
Actions #7

Updated by Vani Kunnatheri 9 months ago

  • Status changed from Resolved to Not Resolved

Technical function and Requirement still appear for changed ASIL Allocation after deallocating from FSR.

Actions #8

Updated by Manoj Kumar 9 months ago

  • Status changed from Not Resolved to Fixed in Dev
Actions #9

Updated by Manoj Kumar 9 months ago

  • Status changed from Fixed in Dev to Resolved
Actions #10

Updated by Vani Kunnatheri 8 months ago

  • Status changed from Resolved to Closed
Actions