Bug #26443

closed

When Approver date format is DD/MM/YYYY then the document is not getting approved from Project Gantt page

Added by malini C over 11 years ago. Updated over 1 year ago.

Status:
Closed
Priority:
High
Start date:
12/20/2013
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

1. Login to the application as Project manager
2. Select a project
3. Attach document
4. Upload output as resource
5. Click on the documents need approval button inside the project plan as Project manager(date format of loged in user should be DD/MM/YYYY)
6. Approve the document
7. CHeck for the status of the document in deliverable info page

MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::

Description

When Approver date format is DD/MM/YYYY then the document is not getting approved from Project Gantt page( Bulk approval option) Working from actions page

Actions #1

Updated by User Admin over 11 years ago

  • Status changed from New to Open
Actions #2

Updated by Jayahari K R almost 2 years ago

  • Status changed from Open to In Progress
Actions #3

Updated by Jayahari K R almost 2 years ago

  • Status changed from In Progress to Resolved
Actions #5

Updated by malini C over 1 year ago

  • Status changed from Resolved to Closed