Actions
Bug #26240
closedProcess VDA - Functional Analysis - While adding multiple Process Item Function and Work element for two different failures, system overlaps on each other.
Start date:
11/16/2013
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1. Login as AQuA Pro Module Administrator
2. Click on the EWQIMS icon and select EVAV NPD/APQP Platform
3. Click on the Products(Aqua Pro) menu
4. Click on the Process VDA menu
5. Select Functional/Failure Analysis menu
6. Right click on the Characteristics and select create Failure option
7. Select multiple Failure without selecting Process Item Function
MODULES:
VDA
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Description
While adding multiple Process Item Function and Work element for two different failures, system overlaps on each other.
Colour for line is displayed in red even if effect is not mapped
Files