Actions
Bug #2535
closedIn Update competency training request, The Date rage is taking (+1 day) from the no of days mentioned
Start date:
08/01/2017
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1. Log into HR pro.
2. Go to competency Tab.
3. Click on Update Competency menu.
4. Click on training request icon in the training column.
5. Enter number of days.
6. Select the date.
7. Observe the date range.
MODULES:
HRPRO
Build Cycle:
Cycle 4
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
In Update competency training request, The Date rage is taking (+1 day) from the no of days mentioned
Files
Updated by Belwinsha A over 7 years ago
- Status changed from Open to Fixed in Dev
Updated by Belwinsha A over 7 years ago
- Status changed from Fixed in Dev to Resolved
Actions