Actions
Bug #20421
closed[Missed By QA] When the default shift is set from PM to AM in the suite then in the project gantt it is showing the duration in - values
Start date:
10/16/2020
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login as Suite admin
2)Click on shifts menu under system tab
3)Create shift from PM to AM shift
4)Now Go To apqp module
5)Open any project
6)Observe the duration
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 6
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Files
Updated by Varadharaj S over 4 years ago
- Status changed from Open to Fixed in Dev
Updated by Varadharaj S over 4 years ago
- Status changed from Fixed in Dev to Fixed with Hotfix
Updated by Anonymous over 4 years ago
- Status changed from Fixed with Hotfix to Resolved
Actions