Actions
Usability #18146
closedProgram: cannot able to select the resource holiday settings To date inside the project view
Start date:
08/17/2020
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login as APQP admin
2)Open the program
3)Select the project from tree list
4)Click on Resource holiday settings icon
5)Click on add
6)Select the To date
7)Observe the issue
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Files
Actions