Steps To Reproduce:
1)Login as Project Manager
2)Click on Resource Tracking menu under Reports tab
3)Observe the error
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
when the plan is awaiting for approval then in the PPAP it is allowing to baseline the project
Files
Updated by Anonymous about 5 years ago
- File resource tracking.png resource tracking.png added
- Tracker changed from Bug to Reports
- Subject changed from when the plan is awaiting for approval then in the PPAP it is allowing to baseline the project to Clicking on resource tracking reports it is showing error.
- Assignee changed from Varadharaj S to Sakthivel P
- Steps To Reproduce updated (diff)
- MODULES APQPPPAP MGR added
- MODULES deleted (
SUPPLIER MANAGEMENT)