Actions
Bug #15282
closedFunctional block for Program BOM import
Start date:
12/30/2019
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login as Program Manager
2)Click on Program menu under Projects Tab
3)Click on New button from the listing
4)Provide program information
5)Select the Pillar Supplier PPAP
6)Click on BOM Import
7)Select the Source file
8)Click on upload
9)Now observe the error - String data truncated
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 2
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
Not able to create program via BOM import. "String or Binary data would be truncated" error is showing up.