PM Supervisor Calendar: PM Supervisor calendar and PM Calendar: The Scheduled, assigned, completed and completed with deadline violate status is not showing in the Planned maintenance detail work order status field as well as in tooltip work order status

Added by Kiruthika G over 5 years ago. Updated over 5 years ago.

Status:
Not Fixed with Hotfix
Priority:
Medium
Assignee:
-
Start date:
10/24/2019
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

1. Login EwQIMS as TPM Module Administrator
2. Click on PM Supervisor Calendar
3. Click on Completed Work order
4. Observe the status
5. Complete the scheduled WO as Supervisor
6. Place the cursor in that WO
7. Observe the assigned person name

MODULES:
TPM
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
SP920
IMPCAT Area If any ::
Impcat Verifed:
Yes

Description

Issue 1: PM Supervisor Calendar: The completed with deadline violated status showing as "completed" in planned maintenance list and Planned Maintenance detail work order status field. -* Closed*

Issue 2: PM Supervisor calendar and PM Calendar: The Scheduled, assigned, completed and completed with deadline violate status is not showing in the Planned maintenance detail work order status field as well as in tooltip work order status field -* Open*

Issue 3: PM Supervisor Calendar--> Planned Maintenance detail screen--> Work order status showing as twice - Closed

Issue 4: PM Supervisor Calendar--> Tool tip--> When a supervisor completed the work order, the name of the assigned person showing as "Project planner" and the assigned person field displays as "assigned Team" -* Open*


Files

Assigned team - Name displays wrong.jpg (144 KB) Assigned team - Name displays wrong.jpg Kiruthika G, 10/24/2019 01:27 PM
Scheduled status - Issue.jpg (122 KB) Scheduled status - Issue.jpg Kiruthika G, 10/24/2019 01:28 PM
Issue 61.jpg (28.4 KB) Issue 61.jpg Kiruthika G, 11/20/2019 02:38 PM
Actions

Also available in: Atom PDF