Actions
Bug #1456
closedVirtual Directory: In Perform audit page, in Submit to auditee button, the first letter of auditee needs to be in capital letter.
Status:
Closed
Priority:
Low
Assignee:
-
Start date:
06/06/2017
Due date:
06/06/2017
% Done:
100%
Estimated time:
0:15 h
Steps To Reproduce:
1. Log into Audit pro as Auditor.
2. Go to Auditor tab.
3. Click on perform audit tab.
4. Enter the desired audit with process mapped to that.
5. Click on Upload audit records.
6. Add the audit attachment.
7. Click on upload button.
8. Give audit status as "NC Identified"
9. Enter Appreciable comments and save it.
10. Create an NC/OFI.
11. Observe the Submit to auditee Button. auditee should be mentioned as Auditee
MODULES:
AUDITPRO
Build Cycle:
Cycle 0
Customer:
NXP (Freescale)
Issue Dependency:
All customers
Dev Commitment to Resolve in::
700
Description
In Perform audit page, in Submit to auditee button, the first letter of auditee needs to be in capital letter.
Files
Updated by Rupa K almost 8 years ago
- File ScreenShot010.png ScreenShot010.png added
Updated by Anonymous almost 8 years ago
- Due date set to 06/06/2017
- Status changed from Open to Fixed in Dev
- % Done changed from 0 to 100
- Estimated time set to 0:15 h
Updated by Anonymous almost 8 years ago
- Status changed from Fixed in Dev to Resolved
Updated by Anonymous almost 8 years ago
- Status changed from Resolved to Fixed with Hotfix
Updated by Anonymous almost 8 years ago
- File Submit to auditee.PNG Submit to auditee.PNG added
Updated by Rupa K almost 8 years ago
Rechecked in NXP DB and it is fixed as Hot Fix
Updated by Anonymous almost 8 years ago
- Project changed from All Customer Issues to EwQIMS SP700
- Status changed from Fixed with Hotfix to Resolved
- Build Cycle changed from Cycle 2 to Cycle 0
- Issue Dependency set to All customers
- Dev Commitment to Resolve in: set to 700
Updated by Anonymous almost 8 years ago
Actions