PM Supervisor and Die PM Supervisor Calendar: The status of planned maintenance should display the status which is showing in the calendar

Added by Kiruthika G over 5 years ago. Updated over 5 years ago.

Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
09/27/2019
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

1. Login EwQIMS as TPM Module Administrator
2. Click on Activities tab
3. Click on PM Supervisor calendar and Die PM Supervisor Calendar
4. Click on Click on Scheduled Worder
5. Observe the status

MODULES:
TPM
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
SP912
IMPCAT Area If any ::
Impcat Verifed:
Yes

Description

PM Supervisor and Die PM Supervisor Calendar: The status of planned maintenance should display the status which is showing in the calendar

Planned Maintenance List:
1. Requested - Scheduled
2. In progress - Assigned
3. Not Completed with delay (Scheduled) - Grey with red
4. Not Completed with delay (Assigned) - Yellow with red
5. Completed with Deadline Violated - Red with Green

Actions #1

Updated by Kiruthika G over 5 years ago

  • Issue Dependency set to SP912
Actions #2

Updated by User Admin over 5 years ago

  • Status changed from New to Open
Actions #3

Updated by Anonymous over 5 years ago

  • Assignee changed from Anonymous to Anonymous
Actions #4

Updated by Anonymous over 5 years ago

  • Status changed from Open to Resolved
Actions #5

Updated by Kiruthika G over 5 years ago

  • Status changed from Resolved to Closed