Actions
Bug #1404
closedIn Layers Screen without entering all the mandatory Fields it throws an alert message as "Duration should be within 365 days"
Start date:
05/31/2017
Due date:
05/31/2017
% Done:
100%
Estimated time:
0:30 h
Steps To Reproduce:
1)Access The Linkhttp://192.168.100.249/EwQIMS1
2)login as scheduler
3)Click on Layers in module setup
4)Enter "Layers name"
5)Select User for layer
6)Enter duration Between audit days "4,or5or,6"
7)Click on save
8)Check the screen shot and observe the result
MODULES:
AUDITPRO
Build Cycle:
Cycle 0
Customer:
Issue Dependency:
636
Dev Commitment to Resolve in::
700
Description
In Layers Screen without entering all the mandatory Fields it throws an alert message as "Duration should be within 365 days" instead it should show Fill in all the Mandatory Fields