Actions
Bug #12355
openResource Utilization: Work order status for the In progress is listing as not completed in Reports
Status:
Open
Priority:
High
Assignee:
-
Start date:
05/27/2019
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1.Login into EwQIMS Application
2.Click on Reports
3.Select Resource Utilization
4.Enter all the mandatory fields
5.Click on View Reports
6.Expand the tabular column
7.The In progress work order status is mentioned as Not completed (Below the PM Delay date)
MODULES:
TPM
Build Cycle:
Cycle 10
Customer:
Issue Dependency:
SP9001
Description
Resource Utilization: Work order status for the In progress is listing as not completed in Reports