closedAIAG VDA Process: After doing any functionality we cannot able to change the PI
Status:
Closed
Priority:
High
Assignee:
-
Start date:
03/07/2019
Due date:
% Done:
100%
Estimated time:
Steps To Reproduce:
1.Login as AQuA Pro Module Administrator
2.Click on AQuA Pro Tab and click on Main Menu
3.Expand the Global PI and select the PI
4.Click on Process FMEA and click on Structure analysis
5.Right click on PI -> click on create process segment
6.Enter Data in process segment field
7.click on Done button
8.Then select another one PI
9.Check for Selected PI
10.Observe the Result
MODULES:
VDA
Build Cycle:
Cycle 4
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
When select one PI and do any of the functionality then we try to change the PI we cannot able to change the PI.
For EX:Click on PFMEA and click Structure analysis then create new process segment and then select another one PI that selected PI will not get changed only the old PI will display.Please verify the attachment.