Actions
Bug #10793
closedDesign and Process FMEA - While adding Risk from VDA failure analysis, Preventive and Detective completion date is not displayed in DFMEA and PFMEA document.
Start date:
01/25/2019
Due date:
% Done:
100%
Estimated time:
Steps To Reproduce:
1.Login as AQuA Pro Module Administrator
2.Click on AQuA Pro Tab and click on Main Menu
3.Expand the Global PI and select the PI
4.Click on Design Documents Menu and click on AIAG VDA DFMEA, new tab will open
5.Click on AIAG VDA Design tab and click on Failure Analysis
6.Right click on child element and select Risk option
7.Add risk data and select Design FMEA
8.observe the completion date
MODULES:
VDA
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
While adding Risk from VDA failure analysis, Preventive and Detective completion date is not displayed in DFMEA document.
Files
Actions