Actions
Bug #6737
closedSilverlight to J-Query Conversion-% completion update by the resource is displayed incorrectly for the project manager view when there is two resource assigned for the task.
Start date:
07/24/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Assign one resource for the task
2)Update the percentage
3)Now add one more resource for the task
4)Check the % percentage in project manager view
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
% completion update by the resource is displayed incorrectly for the project manager view when there is two resource assigned for the task.
1)Assign one resource for the task
2)Update the percentage
3)Now add one more resource for the task
4)Check the % percentage in project manager view
Files
Updated by Anonymous over 6 years ago
- Subject changed from % completion update by the resource is displayed incorrectly for the project manager view when there is two resource assigned for the task. to Silverlight to J-Query Conversion-% completion update by the resource is displayed incorrectly for the project manager view when there is two resource assigned for the task.
Updated by Anonymous over 6 years ago
- Status changed from Resolved to Not Fixed with Hotfix
Updated by Varadharaj S over 6 years ago
- Status changed from Not Fixed with Hotfix to Resolved
Updated by Anonymous over 6 years ago
- Status changed from Resolved to Fixed with Hotfix
Updated by Anonymous over 6 years ago
- Status changed from Fixed with Hotfix to Resolved