Steps To Reproduce:
create a project
assign past dates and current dates to the project and resources to the project
publish the project
open the
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Files
Updated by Anonymous almost 7 years ago
- Status changed from Resolved to Yet to Verify
Updated by Anonymous over 6 years ago
- Project changed from SP810 Dev Build to SP810 - QA build
- Build Cycle changed from Cycle 3 to Cycle 1
Updated by Anonymous over 6 years ago
- File Gantt chart.png Gantt chart.png added
- Status changed from Yet to Verify to Not Resolved
Updated by Anonymous over 6 years ago
When Tasks are assigned with current date, the gantt is not showing the current date tasks. Screenshot attached as why it is not resolved
Updated by Anonymous over 6 years ago
- File gantt chart 2.png gantt chart 2.png added
Updated by Varadharaj S over 6 years ago
- Status changed from Not Resolved to Resolved
Gantt chart Can be anchored to current date only(This is fixed). ( we cannot set for last available task)
Updated by Anonymous over 6 years ago
as per the varadharaj, current date can only be shown