Bug #4851
closedIn Audit Program, once the program manager is changed, it Should not reflect in Re upload approver page,but it is getting changed there too.
100%
1. Log in as Admin.
2. Go to Audit Program page.
3. In define audit Program page enter audit program name and select program manager.
4. Go to audit type and form map tab, map audit type.
5. Go to Map entity and select entity and select Auditee contact person and save.
6. Now go to define audit program and change program manager.
7. Go to map entity page, and click on show all in re upload approver column and observe
Description
In Audit Program, once the program manager is changed, it Should not reflect in Re upload approver page, but it is getting changed there too.
Files
Updated by Anonymous about 7 years ago
- Subject changed from In Audit Program map entity page, if there is 2 Re upload approves is getting removed in Map entity page not in perform audit page it displays both the users. to In Audit Program, once the program manager is changed, it Should not reflect in Re upload approver page,but it is getting changed there too.
- Description updated (diff)
- Steps To Reproduce updated (diff)
Updated by Anonymous about 7 years ago
- Status changed from Open to Resolved
- % Done changed from 0 to 100
In Audit program, if program manager is assigned to audit program it should reflect to re-upload approvers even if the program manager is changed both old and new program manager should be assigned as re-upload approvers.