Actions
Bug #4096
closedWhen importing the completed project,opening the project shows the Percentage completion as 100 for all the task.
Start date:
01/05/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login to EWQIMS application
2)Select APQP module
3)Go TO projects menu
4)Click on import
5)import completed project XML
6)Go To project charter and save imported project (Active)
7)open the project
8)Observe the result.
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 0
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
When importing the completed project,opening the project shows the Percentage completion as 100 for all the task.
Updated by Anonymous over 7 years ago
- Subject changed from Deliverable Type dropdown is displayed as empty.(No 19PPAP Documents details displayed) in the silverlight page to When importing the completed project,opening the project shows the Percentage completion as 100 for all the task.
- Description updated (diff)
- Steps To Reproduce updated (diff)
- Build Cycle changed from Cycle 1 to Cycle 0
Updated by User Admin about 7 years ago
- Status changed from Open to Future Release
Updated by Varadharaj S about 7 years ago
- Status changed from Future Release to Resolved