Actions
Bug #4085
closedGYR/Task Rating: After one publish of a plan document and seeing the task rating it is not updated as per the GYR task rating.
Start date:
01/05/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login to EWQIMS application
2)Select APQP module
3)Go To Projects menu
4)Select and open the project
5)Click on GYR task rating icon
After one publish and periodic update
6)Observe the result
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 0
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
750
Description
GYR/Task Rating: After one publish of a plan document and seeing the task rating it is not updated as per the GYR task rating.
Updated by Anonymous over 7 years ago
- Build Cycle changed from Cycle 1 to Cycle 0
Updated by User Admin about 7 years ago
- Status changed from Suggestion to Future Release
- Dev Commitment to Resolve in: set to 750
This is an issue and needs to be addressed
Updated by Varadharaj S about 7 years ago
- Status changed from Future Release to Resolved
New jquery version came
Actions