Bug #3932
closedCM: ECR form: When implementation section is not selected by the requestor for the completed project, then it allows to create new project with the selected documents as deliverable.
Start date:
01/04/2018
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login into EWIQMS application
2)Go To APQP Module
3)Select the Project
4)Request for Change Management
5)Provide the details
6)Submit the form
7)Observe the result
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
CM: ECR form: When implementation section is not selected by the requestor for the completed project, then it allows to create new project with the selected documents as deliverable.(Auto approval)
Updated by Belwinsha A over 7 years ago
- Status changed from Open to Fixed in Dev
Updated by Belwinsha A over 7 years ago
- Status changed from Fixed in Dev to Resolved