open

In Cloudqa4 System is not allowing to create new audit in new audit schedule. When clicking Add Planned Audit or Add Actual Audit this alert was showing 'EwQIMS : Please click on the Save Audit Schedule button to continue'.

Added by Gayathri P 3 days ago.

Status:
New
Priority:
High
Assignee:
Start date:
04/17/2025
Due date:
% Done:

0%

Estimated time:
Steps To Reproduce:

1.Enter the site URL
2.Enter the user credentials
3.Select Audit module by clicking EWQIMS
4.Click Scheduler menu & select Audit Schedule
5.Select Start date & end date ,enter Audit Schedule name
6.Choose Audit template (Annual audit template / Other Audit type template)- default in annual audit template
7.Click Add actual audit or Add Planned audit