Actions
Feature/Enhancement #30534
openProcess VDA AP values differ from those in the PFMEA and Failure Tree views when using Associate Design Failure or Design Linkage Failures.[Not Replicated in Local]
Start date:
04/08/2025
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1. Login as AQuA Pro Module Administrator.
2. Click on the EWQIMS icon and select EVAV NPD/APQP Platform.
3. Click on the Products(Aqua Pro) menu.
4. Click on the Process VDA menu.
5. Click on the Failure Analysis menu.
6. Select the Production Item->Select segment and click on done.
7. Add Risk (Preverntion).
8.Click on ok button.
9. Observe the result.PFMEA AP and Failure Tree view AP Value should be same (when using DesignFailures or Desing Linkages)
MODULES:
VDA
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
Process VDA AP values differ from those in the PFMEA and Failure Tree views when using Associate Design Failure or Design Linkage Failures.
Files
Updated by Reng Raj about 2 months ago
- Status changed from New to Open
- Assignee changed from chitra Kalangiam to Manivannan Uppiliappan
Updated by Manivannan Uppiliappan about 2 months ago
- Status changed from Open to In Progress
Issue Not Replicating in local
Updated by Manivannan Uppiliappan about 1 month ago
- Subject changed from Process VDA AP values differ from those in the PFMEA and Failure Tree views when using Associate Design Failure or Design Linkage Failures. to Process VDA AP values differ from those in the PFMEA and Failure Tree views when using Associate Design Failure or Design Linkage Failures.[Not Replicated in Local]
Updated by chitra Kalangiam 8 days ago
- Tracker changed from Bug to Feature/Enhancement
WE are expecting Mark support for this so moving to next release
Updated by Manivannan Uppiliappan 8 days ago
- Status changed from In Progress to Suggestion
Actions