Actions
Bug #22997
closedSearch Inspection list : Signoff details pop-up -> Status is showing completed for all users (levels) even if only 1 user approves it
Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
09/08/2021
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1.Go to IC
2.Click on Search Inspection list
3.Select one PI and perform signoff
4.Open the Signoff details pop-up
5.Observe that Status is showing completed for all users (levels) even if only 1 user approves it
MODULES:
IC
Build Cycle:
Cycle 1
Customer:
Husco
Issue Dependency:
IMPCAT Area If any ::
Impcat Verifed:
Yes
Description
Search Inspection list : Signoff details pop-up -> Status is showing completed for all users (levels) even if only 1 user approves it
Actions