Actions
Bug #22159
openAnnual Audit Plan Report ->Inprogress status is not showing in report. If any one actual audit is not completed from the plan (Not Confirmed, awaiting for approval. Waiting for confirmation,Tentative,Scheduled, deadline violated)
Status:
Fixed with Hotfix
Priority:
High
Assignee:
-
Start date:
05/10/2021
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
Annual Audit Plan Report ->Inprogress status is not showing in report. If any one actual audit is not completed from the plan (Not Confirmed, awaiting for approval. Waiting for confirmation, Tentative, Scheduled, deadline violated)
MODULES:
AUDITPRO
Build Cycle:
Cycle 1
Customer:
Issue Dependency:
Skoda-Phase3
IMPCAT Area If any ::
Impcat Verifed:
Yes
Description
Annual Audit Plan Report ->Inprogress status is not showing in report. If any one actual audit is not completed from the plan (Not Confirmed, awaiting for approval. Waiting for confirmation, Tentative, Scheduled, deadline violated)
Updated by Anonymous about 4 years ago
- Status changed from Fixed in Dev to Resolved
Updated by Raja S about 4 years ago
- Status changed from Resolved to Fixed with Hotfix
Updated by Raja S about 4 years ago
- Status changed from Fixed with Hotfix to Not Fixed with Hotfix
Updated by Anonymous about 4 years ago
- Status changed from Not Fixed with Hotfix to Fixed in Dev
Updated by Anonymous about 4 years ago
- Status changed from Fixed in Dev to Resolved
Updated by Raja S about 4 years ago
- Status changed from Resolved to Yet to Verify
Updated by Raja S about 4 years ago
- Status changed from Fixed in Dev to Fixed with Hotfix
Updated by Raja S about 4 years ago
Verified with all status in corporate and multisite