Actions
Bug #20567
closedBug #20450: Task Escalation mail is not generated in the batch manager - working in the previous build
Project Competency: Mandatory options are not highlighted in blue color it is showing in black only and when editing the same the option is showing as "Nice to have" instead of "Mandatory"- New
Status:
Closed
Priority:
Medium
Assignee:
-
Start date:
10/27/2020
Due date:
% Done:
0%
Estimated time:
Steps To Reproduce:
1)Login as Project admin
2)Open the project charter
3)Click on competency icon
4)Add skill
5)Select the mandatory option
6)Click on Save
7)Observe the color code in black
MODULES:
APQPPPAP MGR
Build Cycle:
Cycle 7
Customer:
Issue Dependency:
Dev Commitment to Resolve in::
Description
Edit Experience dialog popup shouls be changed to Edit Experience instead of Add Experience
Files
Updated by Anonymous over 4 years ago
- File 13.png 13.png added
- Subject changed from When the remainder mails alone is enabled then mail is not generated in the batch manager[Upcoming and Pending Remainder] - Issue dependency 20450 to Project Competency: Mandatory options are not highlighted in blue color it is showing in black only - New
- Assignee changed from Raghu Ram to Belwinsha A
- Steps To Reproduce updated (diff)
Updated by Anonymous over 4 years ago
- File 15.png 15.png added
- Subject changed from Project Competency: Mandatory options are not highlighted in blue color it is showing in black only - New to Project Competency: Mandatory options are not highlighted in blue color it is showing in black only and when editing the same the option is showing as "Nice to have" instead of "Mandatory"- New
- Description updated (diff)
Updated by Belwinsha A over 4 years ago
- Assignee changed from Belwinsha A to Anonymous
Updated by Anonymous over 4 years ago
- Status changed from Fixed in Dev to Fixed with Hotfix
Updated by User Admin over 4 years ago
- Status changed from Fixed with Hotfix to Resolved
Actions