Bug #15880
openTime Zone(Subtract date - Enabled & Disabled) - Server date is Central time and the Client IST related issue. Kindly refer description
0%
1.Click on MSA-setup.
2.Click on Gage menu
3.Select Calibration lab as inhouse or External
4.Click on As of Date & pick the date
5.Click on Last study date& pick the date
6.Choose frequency
7.Click on Save menu
8.Observe the screen
Description
Subtract date (Disabled) -* Server date is Central time and the Client IST*
Gage-->(both External lab & In house)
Master-->(both External lab & In house)
Whenever click on Save or Save and Close out menu after entering all mandatory field,As of date ,Last study date and Next due date are reduced(example :As of date as "12-3-2020"after clicking save menu As of date shows "11-3-2020" likewise Last study date and Next due date also reduced ).
Even though When tries to verify this date in gage screen after completing study, again this date are reduced.